This is the latest update from Kieren Couch of Ward Williams Associates – Civil Project Manager for St Erth Multi Modal Hub (a.k.a. St Ives Park and Ride)
1. A30 junction is planned to go live in early March
2. The platform extension is planned to be completed prior to the timetabling change in May
3. The Station building is now complete
4. The Car Parks will be fully operational in time for the timetabling change in May but hoped that the majority of the construction activities will be finalised in early April.