As you may be aware Cormac Surfacing will be carrying out resurfacing work on the B3302 commencing Monday 16th September.
The work will be carried out under a day time road closure which will be carried out in phases.
Phase 1: Commencing Monday 16th September – White Horse to Leedstown – Approximately 2 days to complete.
Phase 2: Commencing Wednesday 18th September – Leedstown – Approximately 5 days to complete
Copies of the diversion routes are below:
Diversion Route Phase 1 click here
Diversion Route Phase 2 click here
Affected residents will have received a letter to notify them of the impending work.
Traffic marshals will be on site to assist road users.
We appreciate that this will cause a great deal of disruption and will endeavour to keep this to a minimum.
If you have any further queries, please do not hesitate to contact me.
Kind Regards
Carol Bardsley | Surfacing Programmer
Cormac | Surfacing